The World Is Run By Those Who Show UpThe Jeffco School Board met on Tuesday to talk about feedback regarding the proposed facilities master plan and give direction to the staff. It was a 7-hour meeting and nearly impossible to briefly summarize, but we’ll do our best.

Why do you need the summary? Because they’re going to vote on these items tonight at 5:30 pm. You can sign up for public comment, and we encourage you to do so if you have strong feelings about any of these items.

Tuesday’s meeting started with a review of TABOR, led by a representative from the Colorado State University Colorado Futures Center. You can look at the presentation here, but the long and short of it is that TABOR has negatively impacted school funding and in districts like Jeffco, taxpayers are now paying more taxes to fund schools than they would have if TABOR hadn’t been enacted. In addition, our schools are being funded at lower levels than they would have otherwise.

Then board members dived into the meat of the discussion: directions for staff regarding the proposed Facilities Master Plan. Two main points stand out:

  1. There is support for moving to a K-5, 6-8 model, but only if it’s done across the district at the same time. Feedback indicated that the community was open to a district-wide change, and board members largely indicated they would support it as well. Staff adjusted the plan accordingly, and with the exception of Jefferson and Alameda, the new plan reflects a K-5, 6-8 configuration, with additions or new buildings planning for that configuration as well.
  2. Board members are very reluctant to close any schools yet, though they are also concerned about balancing budget concerns with the budget challenges posed by smaller schools in aging buildings. Most wanted to see the district work with the school, perhaps to offer programming that might draw kids from the neighborhood back, or to do other work to otherwise give them a chance to grow again.
  3. Budget projects for the future are concerning and funding cuts may be on the way. Jeffco’s lobbyist told the board earlier that he thought funding that reflected inflation + enrollment would be an “optimistic” projection. As a result, the desire to be proactive and financially efficient while also meeting the needs of learning communities is a central point of this conversation.

A few other notes: according to Jeffco’s Communications Director, Diana Wilson, about 800 people participated in the 12 community forums and about 1,100 participated in the telephone town halls. She also pointed out the questionnaire was only to solicit input. (Also note that her department was posting all of the feedback they received, usually shortly after receiving it, and those should all be available for the public to review on the Jeffco Schools facilities master plan page.)

Now, the play-by-play, in an abbreviated fashion.

The board first talked about the proposed K-5, 6-8 configuration. Opportunities include the opportunity for sixth graders to have more access to clubs, electives, advanced math, access to teachers with degrees in math for struggling students, science classrooms, more art, music, theater, and more opportunities that better reflect the “whole child” concept in the Jeffco 20/20 plan.

Concerns include budgets and social readiness, among others. However, staff is recommending a two-year transition plan that would start with a school’s 4th grade students and families. That would allow families time to think about choice enrollment and also allow schools time to plan for what their budget will look like as a K-5 school.

Specific dates for grade reconfiguration weren’t mentioned, though the two-year transition plan suggests that the earliest date for reconfiguration would be 2018-19. If the reconfiguration is to roll out district-wide, that could be even later, since some of the middle schools would require an addition in order to fully accommodate the 6th graders. Terry Elliot mentioned a “rolling implementation,” though board members said they didn’t want to see “piecemeal” reconfigurations.

Student-based budgeting concerns were also addressed. The short version is that SBB models would continue to be flexible. The current model works best with schools of about 500 students and is problematic with elementary schools under 300 students; however, both Superintendent McMinimee and board members made it clear that they didn’t want to see schools negatively impacted. McMinimee said those numbers might change, and that the district might nee to find additional money in other places, perhaps from efficiencies in the district level or a mill levy override, to put additional dollars into SBB.

Board members were especially interested in hearing about how details like art, music, and PE teachers would be accommodated if schools lost a grade, and making sure that elementary schools don’t take a hit with the new reconfiguration. Ron Mitchell accurately noted that the devil is in the details, and that a lot of work will need to be done to make sure we’re not leaving 6th graders in limbo.

Amanda Stevens also asked how this change would affect schools in the Jefferson and Alameda areas that adopted a K-6, 7-12 model last year. The short answer is that those schools would maintain that configuration. There are no plans to move 6th graders to the 7-12 schools.

Here’s the area-by-area breakdown of BOE recommendations. We’re only noting the areas where board members disagreed with current staff recommendations or areas where the staff specifically asked for directions from the board.

  • Alameda

The board wants to keep both Patterson and Kendrick Lakes open, and recommended deferred maintenance for Patterson and a new 576 seat K-5 school for Kendrick Lakes.

  • Arvada

The board agreed with the staff’s new proposal to add six classrooms to Arvada K-8 so that all schools in the area could reconfigure to K-5, 6-8. Brad Rupert also said that Foster had specifically requested the opportunity to stay a K-6 school because of their dual-language program, and the board appeared open to that recommendation as well.

  • Arvada West

The board recommended keeping both Allendale and Campbell open, though this also presents challenges due to space limitations at one site and low enrollment at the other. Allendale’s capacity is 275, and Campbell’s is 365.

Amanda Stevens wanted to hear more about pathways to keeping the small schools sustainable. Ali Lasell wanted to make sure that closures are a last resort, done only after we’ve exhausted all other options. Brad Rupert also expressed concerns that those areas could start growing again as new families move into the area.

Deferred maintenance or a major renovation (though not addition) are possibilities for Campbell. Deferred maintenance, a new school, a major renovation or even an addition could be possibilities at Allendale. The board needed to know more numbers, but was pretty clear that they’re not ready to close schools yet.

  • Bear Creek

The board was comfortable with cabinet recommendations, though they suggested a new Green Gables School might be a better option than a renovation.

  • Chatfield

OK with cabinet recommendations.

  • Columbine

The board wanted to see more deferred maintenance done on Dutch Creek to make the school more competitive with its neighbors.

  • Conifer

OK with cabinet recommendations, though noted that Conifer HS is the only high school without an auditorium and that the addition of one is an equity item.

  • Dakota Ridge

OK with cabinet recommendations.

  • Evergreen

OK with cabinet recommendations.

  • Golden

Not willing to close Pleasant View yet. “Closing a school to me is a last resort, and it is a last resort after we have exhausted all efforts,” Lasell said.

  • Green Mountain

OK with cabinet recommendations.

  • Jefferson

Of note: a phased rebuild is proposed for Jefferson High School. Other suggestions included something like Warren Tech “East” offerings in the area for students.

  • Lakewood

The board recommends keeping Glennon Heights open and considering a boundary change from a nearby school that’s currently over capacity.

  • Pomona

The Little/Parr consolidation also met with a fair amount of discussion. Board members aren’t willing to close either school yet, in part because this is another area that might see growth in the next few years.

Parr attracts a number of students who live just across the street from the Jeffco boundary (in Westminster 50), for whom Parr is a much closer school. Parr also has approximately 100 preschool students. Little has more students and a vocal community that wants to keep that site open as well.

The board’s preference seems to be to keep both school open and build a new 576-seat school at the Parr site, which is a larger site that allows the district to build while keeping students in the current school during construction.

  • Ralston Valley

There was a question about whether an additional high school is needed, but the answer is no, not until there were enough new feeder schools to fill it. They also recommend keeping the proposed Leyden Rock school a priority for phase I.

  • Standley Lake

OK with cabinet recommendations.

  • Wheat Ridge

Here again, the board was reluctant to close any schools yet. Current recommendations are that Kullerstrand stays open and Prospect Valley gets a new school. The board was also in favor of keeping Vivian and Stober open, though those sites present some challenges. Among them: Stober students may need to go offsite for a year in order to renovate or build a new building.

  • Options Schools

Long View will have deferred maintenance for now, and they’ll begin longer discussions about that site in the fall.

 

The last discussion was about a potential mill levy override. Staff presented a list of funding priorities. The first was a potential backfill if the state does in fact cut funding in the next year or two. However, several possibilities were also listed for what the new funding could bring (assuming state funding remains stable):

  • mental health support for schools
  • security and emergency management
  • student-based budget (suggested at $200/student/year)
  • technology
  • compensation
  • charter school needs (note: charters will get full share of the mill levy override automatically; this would be an additional amount above that specifically dedicated to charter school needs)
  • activities and athletics
  • fees (athletics, Outdoor Lab, transportation)
  • full day kindergarten
  • support services

Tonight’s meeting starts at 5:30 pm in the Board Room. If you can’t be there, you can stream the meeting. We know these are big decisions, so we hope to see a lot of you there and voicing your opinion. If you think Jeffco should go ahead with a mill levy override on the ballot, board members need to know that. They also need to know what you would support (or wouldn’t support) as funding priorities.

If you think they need to stick to just asking for a bond to support construction, tell them. If you are concerned about one of the schools that was suggested for closure, be sure to tell them. There are big decisions and challenges ahead, and board members need to hear your voices to know how best to move forward.

Jeffco Proud!